What does an air balancing report tell an office tenant?

On a renovated office floor, ask for the final testing, adjusting and balancing report, usually called a TAB report. It should help you connect a complaint at a particular desk or conference room to a measured outlet. A one-page total for the air handler may hide a shortage in one room and an excess in another.

Follow a room from drawing to reading

Find the drawing revision and room or diffuser identifier. Locate the design airflow and the final measured airflow in cubic feet per minute (CFM). For example, an outlet designed for 200 CFM and measured at 180 CFM is 10 percent below its target. Whether that satisfies the job depends on the project specification. An unlabeled number in a spreadsheet cannot settle it.

Ask how the measurement was obtained

Look for the system mode, terminal setting and notes about access or equipment limits. A measurement taken at full design flow answers a different question from how a conference room performs during a meeting. If partitions moved after balancing, identify the outlets whose room assignments changed. Ask who will verify an inaccessible outlet and document any adjustment.

The NEBB model TAB specification gives an example of reporting requirements. For an office or storefront HVAC review, mark the occupied room and its outlet IDs on the report before describing the comfort issue.